Category: Testing & Commissioning
-
Installation Testing & Commissioning Method Statement for Earthing System
Purpose of this electrical procedure is to define the step by step method to implement the correct practices for the installation pre-commissioning & commissioning of electrical earthing system. Guidelines contained herein shall ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level. The earthing system consists of…
-
ACS Access Control Electronic Security System Installation & Testing Method Statement
This procedure covers installation & testing of access control system including readers, reader interfaces and accessories, to ensure the required quality control activities are done as per project specifications and client requirements. Method statement details the activities, procedure to follow, specialized tooling and safety requirements, applicable to the execution of the construction/installation work in a…
-
Drainage Piping Above Ground Installation Plumbing Work Method of Statement
This method statement describes the procedure for installation of above ground drainage piping system. Document applies to the inward site inspection, installation and inspection methods to be adopted for the above ground drainage piping system. Project manager is overall responsible for the process implementation of the works. The Construction Manager/Site Engineer will be responsible for…
-
Flood Control Plan During Project Testing and Commissioning
This safework procedure helps to provide guidance in carrying out the necessary measures to avoid flooding during testing and commissioning activities at the construction project. Purpose of this method statement is to control the water flooding that may occur during commissioning activities. Necessary Instruments, Equipment & Tools Mechanical Plumbing Tool Kit Flexible Hose / PVC…
-
Method of Testing & Commissioning of Structured Cabling System
The purpose of this method statement shall be to outline the sequence and method of Testing & Commissioning of Structured cabling system. This procedure is one component of a complete testing and commissioning program. This and other procedures will be used, as needed, to provide assurance that testing activities are being conducted as required by…
-
Elevators Lifts Installation Method Statement Including Testing & Commissioning
The purpose of this method statement is to describe the detailed procedure to be followed for the installation, testing and commissioning of Elevator (Lift) at the construction project site. This method statement is prepared also to ensure that concerned persons are familiar with the sequence of activities, utilization of resources and relevant documents in compliance…
-
Method Statement for Fire Suppression System Installation Testing & Commissioning
Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. Obtain approval of the concerned…
-
Method Statement for Installation & Testing of Liquefied Petroleum Gas LPG Piping System & Tank
Below is a brief method statement for installation & testing of Liquefied Petroleum Gas LPG Piping System including the tank. LPG System shall be installed & tested by specialist supplier approved for the project. Ensure all civil works are completed for the area of installation, and clearance is obtained from respective authorities to proceed further. Prior…
-
Method Of Statement For Cleaning Flushing And Passivation Of Chilled Water Piping
This statement provide a method for the cleaning, flushing and passivation for the HVAC chilled water system in the site itself to be followed by the third or independent party. Objective The objective of cleaning, flushing and passivation is to remove debris such as slit, sand, scale, iron oxide deposits, weld slug and other contaminants…
-
Commissioning Report For a Chiller
If you are looking for commissioning report for a chiller then this page is for your below we have given many checklists or reports which are used as commissioning report for a chiller. Below lists give the checks and readings that should be made while making the commissioning report for a chiller. Precommissioning Report For Chiller Chiller installation…