Home / Testing & Commissioning

Testing & Commissioning

Elevators Lifts Installation Method Statement

lifts elevator installation method statement

The purpose of this method statement is to describe the detailed procedure to be follow for the Commissioning of Elevator (Lift) at the project site. This method statement is prepared also to ensure that concerned persons are familiarized with the sequence of activities, utilization of resources and relevant documents in …

Read More »

Method Statement for Fire Suppression System Installation Testing & Commissioning

Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. …

Read More »

Method Of Statement For Cleaning Flushing And Passivation Of Chilled Water Piping

This statement provide a method for the cleaning, flushing and passivation for the HVAC chilled water system in the site itself to be followed by the third or independent part . Objective The objective of cleaning , flushing and passivation is to remove debris such as slit, sand, scale, iron …

Read More »

Commissioning Report For a Chiller

If you are looking for commissioning report for a chiller then this page is for your below we have given many checklists or reports which are used as commissioning report for a chiller. Below lists give the checks and readings that should be made while making the commissioning report for a chiller. Precommissioning …

Read More »

Testing & Commissioning Of Water Supply Piping System Network

Precommissioning Procedure for Water supply system Ensure that the system installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Check that the Water Booster piping network is complete with proper valves, water hammer arrester drains, vents, strainers, pressure switches & instruments in place as per …

Read More »

Testing & Commissioning Of Water Booster Pump Set – Method Statement

The purpose of this safe work method of statement procedure is to define the step by step method to implement the correct practices for the precommissioning & commissioning of domestic Water Booster Pumps through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves …

Read More »

VESDA System Testing and Commissioning Method Of Statement

List of tools required for VESDA system testing and commissioning which should be arranged before starting the work. Portable Hand tools Step Ladder Insulation Resistance Tester Continuity tester Precommissioning Procedure for VESDA System Check the location of installation of the panel is as per the manufacturer’s recommendation & approved shop drawings. …

Read More »

Testing & Commissioning Of UPS System – Method Statement

The UPS System located normally in the LV rooms supports critical telephone & data room sockets, central equipment in the BMS, Server and security rooms etc. for a period of 30 minutes until power is restored. The UPS system provides continuous, regulated AC power to the loads under normal and abnormal conditions, including loss …

Read More »

Method Statement For Fluke Testing & Commissioning Of Telephone Data System

The purpose of this procedure is to define the step by step method to implement the correct practices for the precommissioning & commissioning of Telephone Data System, Structured Cabling System through the guidelines contained herein so as to ensure that the electrical job execution complies with the project requirements and serves the intended …

Read More »

Testing & Commissioning of Sump Pump Sets

Below is a step wise method of statement for Testing & Commissioning of Sump Pump Sets. Precommissioning Procedure for Sump Pumps Ensure that the pump installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Repair all damages to the equipment paint finish. Ensure that …

Read More »