The purpose of this method statement for electrical testing and commissioning is to explain step by step method to implement the correct practices for the precommissioning, testing & commissioning of “LV Switchgear” through the guidelines.
In addition to below precise method of statement, you can find many electrical and ELV system testing and commissioning method statements from our web portal which you can also download as a package or one by one.
If you are interested in downloading full list of method statement for electrical testing and commissioning please visit our section about electrical testing and commissioning.
Electrical testing and commissioning method of LV panel
The below procedure will ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level of consultant, client and end users.
Required Instruments & Tools
- Portable Hand tools
- Step Ladder
- Measuring instruments
- HV Test Kit
- Secondary injection kit
- Insulation resistance tester
- Multimeter
Pre-commissioning Procedure for LV Switchgear
Ensure that the LV Switchgear installation is complete & all mechanical & electrical comments on installation are completed & approved.
Also make sure that no damage has occurred between mechanical completion & precommissioning.
Repair / replace damaged components, if any.
Check for the location of installation is free of any water or construction debris.
Ensure that the Switchgear are properly tagged & identified location wise and service wise as specified.
Make sure that the wiring termination to the LV switchgear are complete & are tight & secure.
Ensure that the outgoing cables (power & control) from the switchgear are terminated in the respective panels & properly tagged & identified.
Also check and ensure that the earthing of the LV Switchgear has been completed.
Ensure that all BMS wiring are completed.
Make sure that the cables to the switchgear are properly tagged & identified.
Ensure that the rating of the breakers (ACB, MCCB, MCB & ELCB) are as per approved shop drawings & schedules.
Check and ensure that overload relays are selected & set as per the actual connected load.
Ensure that the interlocking is done as per the specifications and schematic diagrams.
Make sure that the metering connections are properly completed.
Check manually the breakers are functioning of all the cubicles in the LV switchgear.
Also check proper sliding function of the cubicles in the rails for all draw out modules.
Check the termination of the cables to the bus bars are tightened to the required torque using torque wrench.
Insulation Resistance Test
Isolate all incoming & outgoing cables.
Apply a voltage of 500 volts DC between phase ‘R’ to Earth for 1 minute with phase Y,B & N shorted & earthed & record the values.
Repeat the test for other phases as well.
Power Frequency Voltage Test
Connect the HV lead from step up transformer to R- phase.
Short the Y & B phase and connect to earth.
Also connect the enclosure to earth.
Switch ON the HV test kit control unit & apply the recommended test voltage (by increasing gradually) for 1 minute to R-phase with respect to other phases earthed & grounded.
Record the leak current.
After 1 minute gradually reduce the test voltage to zero & then switch-off the HV test kit.
Discharge the pole & also the HV test kit.
Repeat the test for Y-phase & B-phase & tabulate the results.
Secondary Injection Test
Check the tightness of secondary connections to all the metering circuits.
Inject the nominal secondary values step by step using secondary injection kit to the power scheme & tabulate the output values as per the rating of meters.
Method statement for electrical testing and commissioning for LV Switchgear
Ensure that all the precommissioning checks are carried out successfully.
The incoming supply of the LV switch gear shall be measured for current, voltage, frequency & phase sequence.
Outgoing feeders shall be energized one by one & the supply shall be measured for current, voltage, phase & frequency.
Check the metering functions for proper operation & correct readings.
Now check the earth leakage trip setting.
Check tripping operation of ELCB
Also check the incomer trip setting.
Check the circuit breakers on/off function.
Now check overload relay settings.
Also check timer settings.
Check the interlocking function is as per specified.
Attachments:
- Pre-commissioning check sheet for LV Switchgear
- Commissioning check sheet for LV Switchgear
- Risk Assessment
List of Electrical Testing & Commissioning Method Statements
Download Method Statement For Testing & Commissioning Of MV Power Cables
Testing of LV Power Cables and Wires
Testing & Commissioning Of Lightning Protection & Earthing System
Method Statement For Testing & Commissioning of Transformers
Testing & Commissioning Of MDB, SMDB, DB, MCC & Capacitor Bank
Method Statement For Testing & Commissioning Of Central Battery System
Download Method Statement for Testing & Commissioning Of Bus Duct & Bus Bar Trunking System
Diesel Generator Set Method Statement for Testing & Commissioning
UPS System Method Statement for Testing & Commissioning
Download Lighting Control System LCS Method Statement for Testing & Commissioning
Audio Visual System AV System Method Statement For Testing & Commissioning
Download Method Statement for Disabled Toilet Alarm System DTA Testing & Commissioning
Access Control System ACS Testing & Commissioning Method of Statement
Download Method Statement for Testing & Commissioning Of IP Clock System
Method Statement for Testing & Commissioning Of Structured Cabling System
Download Method Statement For Fire Alarm System Installation Testing & Commissioning
Method of Statement for Testing & Commissioning Of Building Management System BMS
