Procedure For Air Handling Units Pre-Commissioning and Commissioning Method Of Statement

Below is a detailed procedure which can be used for Air Handling Units pre commissioning and commissioning activities for AHU.

Pre-Commissioning Procedure For AHU

Ensure that the AHU installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Sealing between the access panels & the frames shall be checked to ensure that there is no leakage of air.

Repair all damages to the equipment finish paint. Check AHU installed as per the approved shop drawings and manufacturer’s instructions. Verify that proper thermal overload protection is installed in motors, starters and disconnects. Check all chilled water piping, connected to AHU is with proper valve package, drain, air vents, instruments, etc as per the approved shop drawing.

Commissioning Of Air Handling Units AHU