Below is a simple to understand safe work method statement for the Demolition of Existing Boundary Wall before starting a new project or renovation works.
No. | Description of Activity | Responsibility |
1.0 | Ensure all clearances from the concerned Government Department obtain | PE/SE |
2.0 | Selected working area should be barricaded to avoid accidents & damages | PE/Safety Officer |
3.0 | Place signage such as Keep Out, Demolition is going on and Exclusion Zone & Physical Barrier to be erected around the construction area where it is appropriate. | SE/Safety Officer |
4.0
|
RFIA should be raised and ensure its approval prior to start demolition of existing boundary wall. | QC Engr/PE/SE |
5.0 | Demolition will be carried out after approval from Engineers , start the demolition procedure in the corner of the compound wall at west side near entrance gate. | PE/SE |
6.0 | Start cutting of wall panel by panel using electric jack hammer by separating the compound wall from each other. | PE/SE |
7.0 | Demolition will be carried out by excavator/breaker by pulling / breaking the wall inside the proposed site to avoid damage to the newly installed hoarding/media fence. | PE/SE |
8.0 | Demolition will be carried out manually using electric jack hammer, where the access is not clear for Excavator. | PE/SE |
9.0 | Ensure that demolished wall should be cut into pieces as per required weight for cart away to the approved designated disposal area. | PE/SE |
10.0 | Remove all demolished walls at work place area & clean the area in order to have better access. | PE/SE |
11.0 | Raised WIR for complete demolition of existing boundary wall and ensure its approval from client / consultant. | QC Engr/PE/SE |