| 1.0 | Obtain necessary clearances and approvals from Engineers including MEP clearance prior to start work. |
| 2.0 | Proper Scaffolding should be provided for tall walls. It should be inspected and approved by safety officer. |
| 3.0 | RFIA should be submitted and ensure its approval prior to start work. |
| 4.0 | Before Installation ensure wall is free from any hanging equipment and any heavy dust. |
| 5.0 | Floor works Shall be finished before the installation of Acoustic Panels as it may damage the acoustic panel finish otherwise. |
|
6.0 |
Installation of panels will be started after preparation of substrate wall. |
| 7.0 | Adhesive will be applied behind the fabric panel on the wooden strip and on the corner of the wooden frame behind the panels. |
| 8.0 |
The installation of fabric panels of various sizes will be start from one corner of the wall from bottom to top. |
| 9.0 | Inspection request to be submitted after completion of works and ensure its approval. |