Site icon

Safe Work Method Statement For Testing & Commissioning of DX Split Units

Below is given major sections of a safe work method of statement for Testing & Commissioning of DX Split Units.

This is a normal procedure for doing testing activity.

All method statement can be called safe work method statements once we attach a comprehensive risk assessment that covers all tools and equipment procedure of handling.

If you are using this method statement for safe working method of statement purpose we suggest to download complete package from our safe work method statement download page and you can submit the same for client approvals.

Equipment / Tools Required:

Following tools shall be arranged before starting the job.

PROCEDURE FOR TESTING & COMMISSIONING

General Requirements

All the materials received at site shall be as per the approved technical material submittal for DX Split Units to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR.

Any discrepancies, damages etc., should be reported to the supplier for rectification or replacement & to be removed from site immediately.

All construction preliminary inspection/testing works shall be carried out in accordance with the specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.

All installation activities has been approved by the company.

 Material Transport/ Delivery

DX Split Units are normally shipped & dispatch for goods condition and carefully loaded in containers with crating / boxing. Hence, in case of transit damage, supplier must be informed immediately.

Special care must be taken to ensure that units are offloaded from containers. Rough handling can result in damage to the unit.

Use appropriate type of vehicles in transporting the units and that they are protected against mechanical & weather damage.

All the received units shall be checked & inspected to ensure that it is complying with the approved material submittals prior to site storage.

Storage on Site Store

To ensure that deterioration of the DX Split Units does not occur during storage, it is recommended to store the equipment in sheltered conditions that are protected from weather elements and accidental damage.

DX Split Units shall be protected with plastic/ tarpaulin or shall not be removed from the shipping package unless otherwise instructed to do so.

Avoid any mechanical shocks and strokes during handling operations.

All packages for the equipment reaching the site shall be identified as per package list.

Sequence of Testing & Commissioning for the DX Split Units

Safety Requirements

All site safety rules & regulations shall be complied with.

Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the testing & commissioning and shall be recorded.

All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.

The persons using cleaning fluid, solvent cement & any other forms of chemicals have to wear hand gloves.

Ensure only qualified personnel shall install, test & commissioned the equipment.

During testing & commissioning, display warning sign boards to be provided and barricade the area whenever necessary.

Only competent, experienced & trained personnel shall perform all the required activities stated in this method statement.

Ensure that all operatives fully understand the method of these activities.

Preliminary Checks / Pre Commissioning

Before commencement of Testing & Commissioning activity, the supervisor/ engineer must ensure that:

General Testing & Commissioning Procedure for DX Split Units

ATTACHMENTS
Exit mobile version