Category Archives: Plumbing Method Statements

Method Statement for Installation of Underground Drainage Piping System

This document applies to the inward site inspection, installation and inspection methods to be adopted for the underground drainage piping system. The work methods are summarized as follows: Mandatory Equipment Required Measuring tape and setting out markers Electric drill hammer Hack saw cutter Pipe Fitters tool box Certified mobile scaffolds/step ladder uPVC pipes, fittings &… Read More »

Irrigation Pump Installation Method Statement

This document describes the methodology for the Installation of Irrigation pump for the project building to ensure that all concerned persons are familiar with the sequence of activities, utilization of resources, and execution of the works in compliance with applicable Safety and Quality Procedures, and Project Documents and Specification. This method statement is intended to… Read More »

Synthetic Natural Gas SNG System Testing and Commissioning Method Statement

Prior to acceptance and initial operation, all piping installations shall be inspected and pressure tested to determine that the materials, design, fabrication, and installation practices comply with the requirements of this code. Inspection shall consist of visual examination, during or after manufacture, fabrication, assembly, or pressure tests as appropriate. Supplementary types of nondestructive inspection techniques,… Read More »

Synthetic Natural Gas SNG System Installation Method Statement

Below is the list of tools and equiment that shall be required for installation of Synthetic Natural Gas SNG System. Pipes and Tubes Cutter Arc Welding Machine 0xygen and Acetylene set Calibrated Pressure Gauges Standard Tool Kit for Welder Standard Tool Kit for Welding and Brazing Hand Tools (Wrenches) Pressure Testing Pump Setting Out Check and… Read More »

Method Statement for Testing & Commissioning of Calorifiers

The purpose of this method statement is to define the procedure for the on site commissioning of the Calorifiers. This method statement should be read in conjunction with the relevant method statement for installation outlining the responsibility and quality verification to be performed by various parties. Method Statement for Commissioning of Calorifiers The manufacturer’s commissioning Engineer… Read More »

Method Statement for Fire Suppression System Installation Testing & Commissioning

Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. Obtain approval of the concerned… Read More »

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER TOOLS / EQUIPMENT Portable Hand tools Portable Drilling machines Measuring rule An open ended cylinder 250 mm long and approx.150 mm internal dia. A piece of standard 150 mm dia pipe is suitable. A metal rammer 0f 36 to 40 mm dia. and weighing approx.one Kg. Material… Read More »

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD)

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD) Ensured that the proper clearance is available from civil side before commencement of works. Ensured that the work area is clean and safe for carrying out the activities. Prior to start of works, it shall be ensured that the relevant shop drawings and coordination drawings… Read More »

INSTALLATION OF DRAINAGE, RAIN WATER & CONDENSATE DRAIN PIPE WORK

INSTALLATION OF DRAINAGE,RAIN WATER & CONDENSATE DRAIN PIPE WORK On receipt of Drainage & rain water pipes & fittings , the materials shall be handled & stored in line with the following procedure: Pipes will be stacked on a flat surface free from sharp projections, stones or other objects likely to cause point loading or pipe deformation. The… Read More »

METHOD STATEMENT FOR INSTALLATION OF SUMP PUMPS

Below is procedure for the installation of sump pump. Prior to start of installation it shall be ensured that the shop drawings including coordination drawings of the respective area are approved. It shall be ensured that the area is released by civil contractor to proceed with MEP installations. It shall be ensured that the Sump Pumps are… Read More »