Category Archives: Testing & Commissioning

Method of Testing & Commissioning of Structured Cabling System

The purpose of this method statement shall be to outline the sequence and method of Testing & Commissioning of Structured cabling system. This procedure is one component of a complete testing and commissioning program. This and other procedures will be used, as needed, to provide assurance that testing activities are being conducted as required by… Read More »

Elevators Lifts Installation Method Statement

The purpose of this method statement is to describe the detailed procedure to be follow for the Commissioning of Elevator (Lift) at the project site. This method statement is prepared also to ensure that concerned persons are familiarized with the sequence of activities, utilization of resources and relevant documents in compliance with HSE and QA/QC… Read More »

Method Statement for Fire Suppression System Installation Testing & Commissioning

Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. Obtain approval of the concerned… Read More »

Method Of Statement For Cleaning Flushing And Passivation Of Chilled Water Piping

This statement provide a method for the cleaning, flushing and passivation for the HVAC chilled water system in the site itself to be followed by the third or independent party. Objective The objective of cleaning, flushing and passivation is to remove debris such as slit, sand, scale, iron oxide deposits, weld slug and other contaminants… Read More »

Testing & Commissioning Of Water Supply Piping System Network

Precommissioning Procedure for Water supply system Ensure that the system installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Check that the Water Booster piping network is complete with proper valves, water hammer arrester drains, vents, strainers, pressure switches & instruments in place as per final approved shop drawing. Ensure… Read More »

Page 1 of 10
1 2 3 10