Required tools for installation works: Following tools & equipment shall be arranged before installing the FCU's. Fork Lift or Crane with capacity & arrangement in...

413
The purpose of this  safe work method statement is to define the procedure step by step to implement the correct practices for Installation of...
Calorifier Installation Method Of Statement

384
The purpose of this method statement is to define the procedure for the on site commissioning of the Calorifiers. This method statement should be read...

918
Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare...

491
METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER TOOLS / EQUIPMENT Portable Hand tools Portable Drilling machines Measuring rule An open ended cylinder 250 mm long and approx.150...

922
METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD) Ensured that the proper clearance is available from civil side before commencement of works. Ensured...

680
INSTALLATION OF DRAINAGE,RAIN WATER & CONDENSATE DRAIN PIPE WORK On receipt of Drainage & rain water pipes & fittings , the materials shall be handled...

720
Below is procedure for the installation of sump pump. Prior to start of installation it shall be ensured that the shop drawings including coordination drawings of...

2094
The purpose of this Method Statement is to define the procedure step by step to implement the correct practices for Installation of sprinkler & fire...

800
Below equipment's & tools shall be arranged before starting the process of roof waterproofing works. Measuring tape Cylinder fed propane torch Heavy duty press...