Method Statement for Crack Repairing

Background Surface Preparation Conmix dressing plaster LC 11 is a pre mixed sand cement mortar for internal and external use. It is recommended as finishing coats/repairing coats on to Portland cement based background, or render surface. LC 11 is ideal material for dubbing out and leveling of backgrounds or as an thin coat plaster. The… Read More »

Procedure for the Installation of Ventilation Fans

Requirement of Tools for Installation of Fans Following tools and equipment shall be arranged before starting the work of Installation of Ventilation Fans. Fork Lift or Crane with capacity & arrangement in line with the Manufacturer’s , recommendations, pallet mover and as required at site. Hydraulic Trolley Portable hand tools. Portable Drilling Machine/ Grinding Machine… Read More »

Procedure for Installation of Chilled Water Pumps

The purpose of generating this Method Statement is to define the procedure step by step to implement the correct practices of Installation of Chilled Water Pumps through the guide line contained herein so as to ensure that the job execution complies with the requirements and serves the intended function to satisfactory level. Following tools and… Read More »

Installation of Pressurisation Units & Chemical Dosing System

The purpose of generating this Method Statement is to define the procedure step by step to implement the correct practices for Installation of Pressurisation Units & Chemical Dosing System through the guide line contained herein so as to ensure that the job execution complies with the requirements and serves the intended function to satisfactory level.… Read More »

Method Statement for Installation of Grills, Diffusers, Registers & Louvers

The purpose of generating this Method Statement is to define the procedure step by step to implement the correct practices for Installation of Grills, Diffusers, Registers & Louvers through the guide line contained herein so as to ensure that the job execution complies with the requirements and serves the intended function to satisfactory level. Following tools and materials… Read More »

Safe Work Method Of Statement For Installation Of Fan Coil Units FCU’s

Required tools for installation works: Following tools & equipment shall be arranged before installing the FCU’s. Fork Lift or Crane with capacity & arrangement in line with the Manufacturer’s , recommendations, pallet mover and as required at site. Hydraulic Trolley Portable hand tools. Portable Drilling Machine/ Grinding Machine & Angle Cutter. Spirit Level / Level… Read More »

Method Statement for Testing & Commissioning of Calorifiers

The purpose of this method statement is to define the procedure for the on site commissioning of the Calorifiers. This method statement should be read in conjunction with the relevant method statement for installation outlining the responsibility and quality verification to be performed by various parties. Method Statement for Commissioning of Calorifiers The manufacturer’s commissioning Engineer… Read More »

Method Statement for Fire Suppression System Installation Testing & Commissioning

Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. Obtain approval of the concerned… Read More »

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER TOOLS / EQUIPMENT Portable Hand tools Portable Drilling machines Measuring rule An open ended cylinder 250 mm long and approx.150 mm internal dia. A piece of standard 150 mm dia pipe is suitable. A metal rammer 0f 36 to 40 mm dia. and weighing approx.one Kg. Material… Read More »

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD)

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD) Ensured that the proper clearance is available from civil side before commencement of works. Ensured that the work area is clean and safe for carrying out the activities. Prior to start of works, it shall be ensured that the relevant shop drawings and coordination drawings… Read More »