Safe Work Method Of Statement For Installation Of Fan Coil Units FCU’s

Required tools for installation works: Following tools & equipment shall be arranged before installing the FCU’s. Fork Lift or Crane with capacity & arrangement in line with the Manufacturer’s , recommendations, pallet mover and as required at site. Hydraulic Trolley Portable hand tools. Portable Drilling Machine/ Grinding Machine & Angle Cutter. Spirit Level / Level… Read More »

Method Statement for Testing & Commissioning of Calorifiers

The purpose of this method statement is to define the procedure for the on site commissioning of the Calorifiers. This method statement should be read in conjunction with the relevant method statement for installation outlining the responsibility and quality verification to be performed by various parties. Method Statement for Commissioning of Calorifiers The manufacturer’s commissioning Engineer… Read More »

Method Statement for Fire Suppression System Installation Testing & Commissioning

Required Tools/Equipment Multimeter Detector Testing Tool Hilti Machine Drill Machine Pull string Step Ladders Mobile Scaffold Preparation Work Before Installation With the aid of computer software program design the system and prepare isometric drawing. Prepare layout drawing of piping network system and mechanical equipment of SINORIX1230 System. Prepare drawings of detection system. Obtain approval of the concerned… Read More »

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER

METHOD STATEMENT FOR INSTALLATION OF GRP PIPES FOR STORM WATER TOOLS / EQUIPMENT Portable Hand tools Portable Drilling machines Measuring rule An open ended cylinder 250 mm long and approx.150 mm internal dia. A piece of standard 150 mm dia pipe is suitable. A metal rammer 0f 36 to 40 mm dia. and weighing approx.one Kg. Material… Read More »

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD)

METHOD STATEMENT FOR INSTALLATION OF WATER SUPPLY PUMP (HOT & COLD) Ensured that the proper clearance is available from civil side before commencement of works. Ensured that the work area is clean and safe for carrying out the activities. Prior to start of works, it shall be ensured that the relevant shop drawings and coordination drawings… Read More »

INSTALLATION OF DRAINAGE, RAIN WATER & CONDENSATE DRAIN PIPE WORK

INSTALLATION OF DRAINAGE,RAIN WATER & CONDENSATE DRAIN PIPE WORK On receipt of Drainage & rain water pipes & fittings , the materials shall be handled & stored in line with the following procedure: Pipes will be stacked on a flat surface free from sharp projections, stones or other objects likely to cause point loading or pipe deformation. The… Read More »

METHOD STATEMENT FOR INSTALLATION OF SUMP PUMPS

Below is procedure for the installation of sump pump. Prior to start of installation it shall be ensured that the shop drawings including coordination drawings of the respective area are approved. It shall be ensured that the area is released by civil contractor to proceed with MEP installations. It shall be ensured that the Sump Pumps are… Read More »

METHOD STATEMENT FOR INSTALLATION OF SPRINKLER & FIRE FIGHTING SYSTEM PIPEWORK &  ACCESSORIES

The purpose of this Method Statement is to define the procedure step by step to implement the correct practices for Installation of sprinkler & fire fighting pipework & accessories through the guidelines contained herein so as to ensure that the job execution complies with the requirements and serves the intended function to satisfactory level. Portable Hand tools Portable… Read More »

Method Statement for Roof Water Proofing in Steps with Responsibility Matrix

Below equipment’s & tools shall be arranged before starting the process of roof waterproofing works. Measuring tape Cylinder fed propane torch Heavy duty press rollers Cotton waste  Paint roller and paint brush  Paint roller and paint brush Heavy duty scissors Thinner or solvent cleaner Broom brush Hand gloves Method Statement for Roof Water Proofing in… Read More »