Fire Pump Testing and Commissioning Procedure for Jockey Pumps

Below is the precise procedure for fire pump testing and commissioning procedure – jockey pumps as part of the Fire Fighting System.

Pre Commissioning Procedure for Fire Fighting Jockey Pumps

Ensure that the pump installation is complete and mechanical completion is approved.

Make sure that no damage occurs between mechanical completion & pre commissioning, if any repair all damages to the equipment and paint / finish.

Ensure that the pumps are identified location wise and service wise.

Make sure that the fire fighting system is cleaned internally & externally.

Check again the alignment of pump and driver shaft and make sure these are complying with manufacturer installation instructions.

Note the details of each motor such as make, model number, frame size, kW rating and RPM.Fire Pump Testing and Commissioning Procedure for Jockey Pumps

Check that the Fire Fighting piping network is complete with proper valves, drains, vents, strainers, pressure switches & instruments in place.

Ensure that the Fire Fighting network is hydraulically pressure tested and approved.

Check and make sure that the pump bearings are lubricated/greased as per manufacturer recommendation.

Ensure the pump shafts are rotated by hand freely.

Make sure that electrical power connections with control panel, pressure switch & earthing are done and installation is approved.

Ensure that the field wiring is pre-tested for continuity and insulation resistance.

Ensure that all the relevant valves are in open position.

Check the rotation of motor shaft movement by hand.

Check identification and labeling for equipment in compliance with project specifications.

Commissioning Procedure for Jockey Pumps

Ensure that all the pre-commissioning checks are carried out successfully.

Open the suction valve & allow water to flow into the pump.

Start the pump and record the discharge pressure.

Observe leakage from stuffing boxes and adjust the flow for lubrication of packing.

Check pumps for overheating physically by hand.

Check for any undue vibration/noise.

Check current, voltage & rpm of the motor & record the values.

Plot the pump actual performance curve.

Manufacturer’s installation and operational instructions shall be fully followed during jockey pump testing commissioning.

ATTACHMENTS

  • Pre-commissioning check sheet for Jockey Pumps
  • Commissioning check sheet for Jockey Pumps
  • Performance Record for Jockey Pumps
  • Risk Assessment