Category: Plumbing Method Statements
-
Water Booster Pump Installation Specification & Requirements
The purpose of this plumbing method statement is to describe the methodology for installation of booster pumps for cold water and to detail the steps to be taken to meet the HSE requirements specified for the execution of the project activities. HSE Requirements All personnel working at site shall attend HSE induction / awareness training…
-
Pipe Welding Procedure
The purpose of this method statement / pipe welding procedure is to define and outline proposals for carrying out the welding & installation of MS piping System. Method is applicable to all ERW, Black Steel, Schedule 40, Grade ‘B’ and fittings, in accordance with mechanical specifications for pipe sizes 65mm dia. and above. The work…
-
High Density Polyethylene Pipe HDPE Piping Installation Method of Statement
The purpose of this plumbing method statement is to identify the requirements/methodology for installation of High Density Polyethylene Pipe / HDPE Pipe and fittings in as per the project specifications, drawings and the local regulations as applicable. Over all it is the responsibility of site plumbing engineer and foreman to ensure that the HDPE pipe…
-
Fire Hose Reel Testing and Commissioning Method Statement
Below is a precise method statement for fire hose reel testing and commissioning part of project fire fighting system. Automatic wet system is a system that is attached to a water supply capable of supplying the system demand at all fires and that requires no action other than opening a hose valve to provide water…
-
Basement MEP Coordination Shop Drawing Preparation and Checklist
The purpose of preparing the basement MEP coordination drawings is to prevent the clashing of MEP services during the execution of MEP works at a construction project site. Also to prevent the MEP service form coming below the Minimum clearance required for the cars in the driveway and parking as per the requirements of the…
-
Safe Work Method Of Statement For Dewatering Work
This Method Statement provides the control sequence of construction and methodology that will be used for the supply, installation and maintenance of dewatering system over the entire project at any stage based on the following data: Required Data: Water Table level : m Depth of excavation : -2.30m (Gen) Depth of excavation : -3.30m / 5.50m…
-
Risk Assessment for Drainage Pipes Installation
Construction and HSE team must ensure that hazard identification is complete before start of the drainage piping work. The construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that risks have well established legal requirements, potentially high risks). Construction and HSE team to prepare the risk assessment…
-
Pump House / Pump Room Piping & Pumps Installation Method Statement
Purpose of this mechanical safework method of statement is to ensure that correct materials are used and agreed procedures are implemented during fabrication, welding, installation and testing of the pump room piping network. This method statement specifies the sequence and methodology for the installation and testing of piping to achieve the best quality of work.…
-
Drainage Piping Above Ground Installation Plumbing Work Method of Statement
This method statement describes the procedure for installation of above ground drainage piping system. Document applies to the inward site inspection, installation and inspection methods to be adopted for the above ground drainage piping system. Project manager is overall responsible for the process implementation of the works. The Construction Manager/Site Engineer will be responsible for…