Category Archives: Plumbing Method Statements

Fire Pump Testing and Commissioning Procedure for Jockey Pumps

Below is the precise procedure for fire pump testing and commissioning procedure – jockey pumps as part of the Fire Fighting System. Pre Commissioning Procedure for Fire Fighting Jockey Pumps Ensure that the pump installation is complete and mechanical completion is approved. Make sure that no damage occurs between mechanical completion & pre commissioning, if any… Read More: Fire Pump Testing and Commissioning Procedure for Jockey Pumps »

Fire Fighting System Hose Reel & Sprinkler System Testing & Commissioning

The purpose of this procedure is to define the step by step method to implement the correct practices for the precommissioning & commissioning of “Fire Fighting System” through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level. Pre Commissioning Procedure for Fire… Read More: Fire Fighting System Hose Reel & Sprinkler System Testing &… »

grp pipe installation method statement

Below is a detailed grp pipe installation procedure which is applicable for any kind and size of project. Arrange below tools and equipment before starting grp pipe installation works. Portable Hand tools Portable Drilling machines Measuring rule An open ended cylinder 250 mm long and approx.150 mm internal dia. A piece of standard 150 mm dia… Read More: grp pipe installation method statement »

Pipe Welding Procedure

The purpose of this method statement / pipe welding procedure is to define and outline proposals for carrying out the welding & installation of MS piping System. Method is applicable to all ERW, Black Steel, Schedule 40, Grade ‘B’ and fittings, in accordance with mechanical specifications for pipe sizes 65mm dia. and above. The work… Read More: Pipe Welding Procedure »

Safe Work Method Of Statement For Dewatering Work

This Method Statement provides the control sequence of construction and methodology that will be used for the supply, installation and maintenance of dewatering system over the entire project at any stage based on the following data: Required Data:  Water Table level :  m Depth of excavation : -2.30m (Gen) Depth of excavation : -3.30m / 5.50m… Read More: Safe Work Method Of Statement For Dewatering Work »

Method Statement For Testing & Commissioning Of Electric Water Heaters

The purpose of this procedure is to define the step by step method to implement the correct practices for the pre-commissioning & commissioning of “Electric Water Heater”. Through the guidelines contained herein so as to ensure that the job execution complies with the project requirements and serves the intended function to satisfactory level. Pre-Commissioning Procedure for Electric Water… Read More: Method Statement For Testing & Commissioning Of Electric Water Heaters »

Method Statement & Specifications For Mechanical Sound, Vibration & Seismic Control Installations

DESCRIPTION OF WORK This specification covers all sound & vibration isolators for mechanical equipment to prevent the transmission of vibration and mechanically transmitted sound to the building structure. It also includes adjusting each mounting system, and measurement of isolator system performance when so requested by the Consultant. Specific mounting arrangements for each item of mechanical… Read More: Method Statement & Specifications For Mechanical Sound, Vibration & Seismic… »