Below is step wise procedure or method statement for the installation of calorifier. Ensure all civil works are completed for the area of installation, and clearance is obtained from respective authorities to proceed further. Prior to start the installation, refer to the approved
Read Full Method Statement
1. PURPOSE The purpose of generating this Method Statement is to define the procedure step by step to implement the correct practices for Installation of Electrical Water Heater through the guide line contained herein so as to ensure that the job execution complies with
Read Full Method Statement
Precommissioning Procedure for Water supply system Ensure that the system installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Check that the Water Booster piping network is complete with proper valves, water hammer arrester drains, vents,
Read Full Method Statement
The purpose of this safe work method of statement procedure is to define the step by step method to implement the correct practices for the precommissioning & commissioning of domestic Water Booster Pumps through the guidelines contained herein so as to ensure that the
Read Full Method Statement
Below is a step wise method of statement for Testing & Commissioning of Sump Pump Sets. Precommissioning Procedure for Sump Pumps Ensure that the pump installation is complete and mechanical completion is approved. Ensure that no damage occurs between mechanical completion & precommissioning. Repair all
Read Full Method Statement