Method Statement for Cubicles & Lockers Installation

Following tools shall be arranged before start of the work.

  • Spirit Level
  • Alignment line
  • Drill machine
  • Chalk line
  • Hammer
  • Set of screw drivers

Below is Method Statement for Cubicles & Lockers Installations

Obtain necessary clearances and approvals from Engineers including MEP clearance. Ensure the area to receive the cubicles will be thoroughly cleaned and it will be made free from any dust loose lying debris, and hanging material on walls.

  • Check lines and levels of finished walls and floors.
  • Take site measurements, prepare computerized drawings and fabricate cubicles accordingly
  • Ensure all other trade work is over, such as ceiling works, floor and wall tile work, painting
  • Install section wise to uniform lines and levels. Ensure equal spacing
  • Check for proper operation of all accessories & unit as a whole
  • Inspection request to be submitted after completion of works and ensure its approval Lockers
  • Obtain necessary clearances and approvals from Engineers including MEP clearance
  • Ensure the area to receive the Lockers will be thoroughly cleaned and it will be made free from any dust loose lying debris, and hanging material on walls
  • Check lines and levels of finished walls and floors.
  • Take site measurements, prepare computerized drawings and fabricate cubicles accordingly’
  • Ensure all other trade work is over, such as ceiling works, floor and wall tile work, painting
  • Install section wise to uniform lines and levels. Ensure equal spacing
  • Check for proper operation of all accessories & unit as a whole
  • Inspection request to be submitted after completion of works and ensure its approval